Town of Wareham
Sewer Construction Schedule

Week Ending September 25, 2009
        Crew #1
                Parkwood Drive - SMH 10A to 10B
        Crew #2
                Crab Cove Terrace - SMH 23E - 27E
        
        
Week Ending October 2, 2009
        Crew #1
                Parkwood Drive - SMH 10A to 10C to 30A (Hazel Street)
        Crew #2
                Crab Cove Terrace - SMH 23E - 27E 2" PVC Force Main
        

Ongoing Activities
        Inverts
        Paving / Gravel
        Cleaning Pump Station Sites
        Testing
        


SCHEDULE SUBJECT TO CHANGE

 
Town of Wareham