Town of Wareham
Sewer Construction Schedule
Week Ending September 25, 2009
Crew #1
Parkwood Drive - SMH 10A to 10B
Crew #2
Crab Cove Terrace - SMH 23E - 27E
Week Ending October 2, 2009
Crew #1
Parkwood Drive - SMH 10A to 10C to 30A (Hazel Street)
Crew #2
Crab Cove Terrace - SMH 23E - 27E 2" PVC Force Main
Ongoing Activities
Inverts
Paving / Gravel
Cleaning Pump Station Sites
Testing
SCHEDULE SUBJECT TO CHANGE
|