Town of Wareham
Sewer Construction Schedule
Three (3) Week Schedule Look Ahead
Linwood / Ladd Avenue, Tempest Knob and Parkwood Beach Sewers
Job #312 - Contract No. 1
Week Ending April 30, 2010
1. Indian Neck, Linwood, Oak Street & Parkwood Drive Pump Stations
a. Paving Crew Loam & Sead, Install Binder
b. Grassetti installing Control Cabinets, Wiring, Setting Generators, Installing
Pumps at Oak Street & Indian Neck. Complete Mechanical on Valve Vaults,
Indian Neck & Oak Street.
Week Ending May 7, 2010
a. Grassetti Working on Pump Stations, Wiring, Mechanical, Guide Bars, Float
Switches, Valve Supports, etc.
b. Gas Services to Pump Stations?
Power to Stations?
Week Ending May 14, 2010
a. Fence around Pump Stations
b. Plantings around Pump Stations
c. Grassetti complete (Power & Gas?)
Job #312 - Contract No. 1
Week Ending April 30, 2010
1. Installing 8" PVC Sewer on Cromesett Road 4c-5a
Week Ending May 7, 2010
1. Installing 8" PVC Sewer on Cromesett Road 5a-5d
Week Ending May 14, 2010
1. Installing 8" PVC Sewer on Cromesett Road 5d-5e
2. Installing 8" PVC Sewer on Marks Cove Road 5e-6a
3. Installing 8" PVC Sewer on Marks Cove Road 5e-7a
SCHEDULE SUBJECT TO CHANGE
|