Town of Wareham
Sewer Construction Schedule
Three (3) Week Schedule Look Ahead
Job #320 - Contract No. 2
Week Ending May 14, 2010
Fence Installation at Pump Stations
Electrical Wiring between Control Panel and Generator
Gas Services to Parkwood & Oak Street Pump Stations
Week Ending May 21, 2010
Landscaping / Planting at Pump Stations Sites
Mechanical Piping at Valve Vaults, Riser Pipe for Pumps
Electrical Wire Pumps / Float Switches, Install Parkwood Control Panel
Gas Meter Supports Installed, Pipe Gas to GEnerator / Inspection
Week Ending May 28, 2010
Installation of Gates on Fences
Finish Loaming and Seeding Disturbed Areas at Pump Station
N-Star Power?
National Grid Service to Indian Neck?
a. Fence around Pump Stations
b. Plantings around Pump Stations
c. Grassetti complete (Power & Gas?)
Job #312 - Contract No. 1
Week Ending May 14, 2010
Cromesett Road SMH 5c-e
Week Ending May 21, 2010
Cromesett Road 12" RCP Drain
8" Stub Twins Beach Lane
Marks Cove Road 5e-6a
Week Ending May 28, 2010
Marks Cove Road 6a - 2' PVC Force Main
Marks Cove Road 5e - 7a
Marks Cove Road 7a - 2' PVC Force Main
SCHEDULE SUBJECT TO CHANGE
|