Town of Wareham
Sewer Construction Schedule

Three (3) Week Schedule Look Ahead


Job #320 - Contract No. 2

Week Ending May 14, 2010

Fence Installation at Pump Stations
Electrical Wiring between Control Panel and Generator   
Gas Services to Parkwood & Oak Street Pump Stations

        
Week Ending May 21, 2010
        
        Landscaping / Planting at Pump Stations Sites
        Mechanical Piping at Valve Vaults, Riser Pipe for Pumps
        Electrical Wire Pumps / Float Switches, Install Parkwood Control Panel
        Gas Meter Supports Installed, Pipe Gas to GEnerator / Inspection


Week Ending May 28, 2010
                
        Installation of Gates on Fences
        Finish Loaming and Seeding Disturbed Areas at Pump Station
        N-Star Power?
        National Grid Service to Indian Neck?
        a. Fence around Pump Stations
                b. Plantings around Pump Stations
                c. Grassetti complete (Power & Gas?)





Job #312 - Contract No. 1

Week Ending May 14, 2010

        Cromesett Road SMH 5c-e

Week Ending May 21, 2010

        Cromesett Road 12" RCP Drain
        8" Stub Twins Beach Lane
        Marks Cove Road 5e-6a

Week Ending May 28, 2010

        Marks Cove Road 6a - 2' PVC Force Main
        Marks Cove Road 5e - 7a
        Marks Cove Road 7a - 2' PVC Force Main


SCHEDULE SUBJECT TO CHANGE

 
Town of Wareham