Town of Wareham
Sewer Construction Schedule

Contract No. 1 & 2
Wareham, MA

Job #312 - Contract No. 1

July 6, 2010
Crew #4

Pump Station Preliminary Start Up.
        
July 12, 2010 to July 23, 2010
        
Pump Station Start Up

July 19, 2010
Crew #5

Pump Station Start Up
                
                




Job #320- Contract No. 2

July 6, 2010
Crew #1

Indian Neck Road pipe installation SMH13a-14d to week ending July 23, 2010

        

SCHEDULE SUBJECT TO CHANGE

 
Town of Wareham