Town of Wareham
Sewer Construction Schedule
Contract No. 1 & 2
Wareham, MA
Job #312 - Contract No. 1
Week Ending:
September 10, 2010
Miscellaneous Cleanup: Ivy, Bayside, Hazel, Gardonia, Fir, Elwood, and Datewood Streets
September 17, 2010
Miscellaneous Cleanup: Chestnut, Bird, Ash, Parkwood, River Terrace and Crab Cover Terrace.
This will complete the restoration work.
September 8, 2010
Pump Station Start Up and Testing
Generator Startup? Waiting for Parts (Will Advise)
Job #320- Contract No. 2
Week Ending:
September 10, 2010
Mayflower Road 13E - 15B
Install Precast Vault and Tapping Sleeve and Valve for Surge Arrestor System.
September 17, 2010
Mayflower Road 15B - 15D
September 24, 2010
Mayflower Road 15D - 16A
September 10, 2010
Paving curb to curb, Mark's Cove Road, Sippican, Cedar Island, and Connehesett Road
September 10 & 17, 2010
Aguila Construction Co. - Raising Covers and Inverts
SCHEDULE SUBJECT TO CHANGE
|  |