Town of Wareham
Sewer Construction Schedule
Week Ending August 7, 2009
Crew #1
Gardenia Street - SMH 18B to 18C
Crew #2
Narrows Road / Indina Neck - SMH 5C to 9A - 8" Force Main
Crew #3
Larch Street - 8" DI Water Misc. Drain
Service Crew
Parkwood Drive - SMH 20A to 20C - Installing Wells
Week Ending August 14, 2009
Crew #1
Parkwood Drive - SMH 18C to 20C & SMH 18C to 30B
Crew #2
Oak Street - Services
Crew #3
Larch Street - Sewer 7 Water Services
Service Crew
Oak Street / Thatch Street - Services
Week Ending August 21, 2009
Crew #1
Parkwood Drive - SMH 20A to 20C
Crew #2
Teakwood / Elmwood - SMH 23A to 23E
Crew #3
Chestnut Street - SMH 26A to 26E
SCHEDULE SUBJECT TO CHANGE
|